Project Name: Elevated Water Storage Tank Rehabilitation

Project Number: W0218-005-01

GEFA Loan Number: DW2023041

Bid Date: Friday, August 23, 2024, at 11:00 AM   Friday, September 13, 2024, at 11:00 AM

Work to be Done: 

The work to be done shall consist of furnishing all labor, materials and equipment necessary to construct the proposed Elevated Water Storage Tank Rehabilitation as specified. In general, construction consists of miscellaneous tank repairs and interior and exterior painting, including draping, blasting, disposal of lead-based paint, and all associated measures for the (1) Leg Tank and (1) Pedestal Tank. Time allotted for completion of work is 180 consecutive calendar days to substantial completion. Work shall be complete and ready for contract closeout with 194 consecutive calendar days. All work shall be completed in accordance with the plans and specifications. The work will be awarded in one (1) Contract.

Engineer’s Estimate:  $ 400K